CHG0052183 - Planned at Risk Network Maintenance Newcastle Central NE-1 IP Fabric | Tuesday 15/04/2025 2100 BST - Wednesday 16/04/2025 0100 BST

Scheduled Maintenance Report for Pulsant Service

Completed

The scheduled maintenance has been completed.
Posted Apr 16, 2025 - 01:00 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 15, 2025 - 21:00 BST

Scheduled

Dear Client,

Please be aware of the following planned network maintenance.

What:
As part of Pulsant’s lifecycle management, the Network Infrastructure team will be performing a core network maintenance on our IP Fabric switches located in Newcastle Central NE-1. As with any maintenance activity, there is an element of risk, although there is no expected impact to service for resilient services. Pulsant engineers will extend the post maintenance monitoring window to provide additional support for the monitoring team.

Why:
This work is required to upgrade the software on our switching fabric at the recommendation of the vendor and is in keeping with Pulsant device lifecycle policy.

When:
The maintenance will take place during the following window:

Start: Tuesday 15/04/2025 21:00 BST
End: Wednesday 16/04/2025 01:00 BST

If you have any questions, please raise a ticket by emailing support@pulsant.com or by calling our support team directly.

For your reference, please see our status page for updates on planned maintenance and service incidents. This can be found at http://status.pulsant.com

Please accept our sincere apologies for any inconvenience this may cause.


Regards,
Pulsant Support Team
0345 119 9999
Posted Apr 07, 2025 - 11:27 BST
This scheduled maintenance affected: Data Centre Services (NE-1 - Newcastle Central) and Managed Networks (Newcastle).