2018-1284 - Fire Systems Cause and Effect at our Maidenhead Facilities
Scheduled Maintenance Report for Pulsant Service
Completed
The scheduled maintenance has been completed.
Posted Jan 27, 2018 - 17:00 GMT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 27, 2018 - 09:00 GMT
Scheduled
Dear Customer,

We will be undertaking a Full cause and effect testing of our fire systems at our Maidenhead facilities. This will be covering all areas at our facility in line with regulatory and legal requirements.


WHAT
In keeping with legislation and Pulsant planned and preventative maintenance regime, we will be carrying out a full cause and effect testing of our Fire Alarm system at our Maidenhead facilities. This will involve full testing of the audible system and protection systems to ensure all aspects work to design. There will be no physical deployment of fire suppressant just ensuring that all notifications, zones and alarm states are correctly configured.


SERVICE IMPACT
NONE No service impact is planned, however there will be a number of audible tests and scenarios executed to ensure fire systems and infrastructure responds in the appropriate manner. As with any switching or change in state there is an "At Risk" period, so as a matter of courtesy we are informing all our customers.


WHY
In line with Pulsant planned preventative maintenance program and bound by regulatory requirements, Pulsant will be completing a program of inspections, testing of the fire alarm systems that support the site.

WHEN
To mitigate disruption to the customer base, the essential works will be undertaken during the weekend and during the following maintenance window period: -

Saturday 27th January 2018 between 09.00 GMT to 17.00 GMT:-

The "At Risk" windows during these works will be kept to an absolute minimum and normal service restored at the earliest opportunity.

If there are any queries or concerns of the planned works, please contact Pulsant Support or your account manager. Pulsant wish to thank you for patience and understanding during these essential works.

A final broadcast will be sent out post completion of all the works confirming that full normal service has been resumed.

Regards,
Pulsant Support Team
support@pulsant.com
0845 1199 999
Posted Jan 10, 2018 - 14:28 GMT