2017-1552 Planned Network maintenance has now been completed, should you believe there are issues following this, please let us know on 0345 119 9999 or via support@pulsant.com
Posted Nov 10, 2017 - 23:22 GMT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 10, 2017 - 22:15 GMT
Scheduled
WHAT?
We have been advised by our vendor to carry out a software upgrade to our F5 Loadbalancer platform at our Milton Keynes data centre.
To mitigate impact to service, we will be failing over to an upgraded F5 which is a sub second process. This will result in a reset of any current connections as the device fails-over. Reset connections will be re-established through the active device.
WHY?
This is part of our regular software update cycle to ensure security and stability.
WHEN?
The maintenance will take place during the following window:
Start: 10/11/2017 22:00 GMT
End: 11/11/2017 03:00 GMT